Hi,
When i run T Code TPM44, the following messages are appeared
1) There are planned flows for position SA=RBI,SE=949,CC=9999,VA=001,PT=04I,AC=0001, on or before key date 18.10.2014
Message no. TPM_AD101
Procedure
Post the planned profit-related flows before creating the closing report.
2)Create account 42000010 for 18.10.2014 as a cost element in controlling area AD01
3) Error in update to Accounting; see log
Message no. TPM_TRAC1153
4) There are planned flows for position SA=RBI,SE=949,CC=9999,VA=002,PT=04I,AC=0001, on or before key date 18.10.2014
Message no. TPM_AD101
5) There are planned flows for position SA=RBI,SE=949,CC=9999,VA=003,PT=04I,AC=0001, on or before key date 18.10.2014
Message no. TPM_AD101
6) Create account 42000010 for 18.10.2014 as a cost element in controlling area AD01
With regards
raju