Hello Ms Jayabalan Kamala
The problem is with the Termination or closure of the contract not done properly by your side. Hence please go to FTR_EDIT, book for closure of the contract. After closure of the contract, please proceed as you wish for TPM2 and fix up your problem. Please remember that after fixing up your problem when you try to intend to run TBB1 your contract would not allow you to do that. After that you again need to make a conditional reversal of the entire contract from termination side to level 2 as contract settlement (as if it is in the stage of original contract) then you run TBB1, TPM60 and TPM1 and repost the valuations. It would work for you, please check and confirm..
regards
Anand