Dear Guru,
We are currently upgrading from 4.6c to ECC6.0 EHP5 , and from what I studied
from Migration guide and all note . I has
a question in step TPM_MIGRATION_CAT and tpm_migration as follow
please kindly suggest
1) I choose conversion type = 3 , is it correct??
2) in this program they required us to fill in logical
destination of production system , customizing system and test system . I’m not
sure whether which one I should enter in this field between old system (4.6) and
new system(ECC6)
3)from the requirement I got , I plan to activate
EA-FS , as it is a prerequisite for business partner
conversion and to activate FIN_TRM_LR_FI_AN and FIN_TRM_LR_FI_AN_2 for Enable
premium/discount function
I’m not sure the sequence, which one I should activate first,
do I need to activate it both at the same time ??
4) from the migration guide page 23 , Preparations step for
conversion steps
“You will need to make a number of very important settings before you begin with the Conversion”
Does this mean that , I have to follow the steps 8.2 on ECC6.0 or on 4.6C??
5) once i finish conversion on Dev environment , do i need to do TPM_migration on test and production system again??
Can i use the transport request that is created in development environment??
Thank you in advance